We are excited to be working with Ogden City on another one of their projects. This work is located at 28th Street: Grant Ave to Lincoln Ave. Lincoln Ave: Doxey St to 27th St. We began this project back in May 2024 and are expected to be completed October 2024.
The work to be performed consists of furnishing and installing the equipment, facilities, services and appurtenances which includes, but is not limited to, the following: Install approx. 780 ft of 29”x45” elliptical RCP Storm main, 560 ft of 15” RCP storm main, storm combo boxes and catch basins. Install approx. 1,030 ft of 8” PVC water main, 1,200 ft curb and gutter, and 5,800 SF concrete flatwork.