City Creek Block 75 Project

Salt Lake City, UT

We Are Working On This Project With Big-D Construction Along With Many Other Companies. This Is A Big Project For Us And Are Grateful For the Opportunity To Prove That We Can Play With The Big Boys!

We First Started This Project Back In March 2008 . Since Then The First Part Of The Mass Excavation Is 100% Complete. We Were Also Awarded The Ramp Construction On 100 South And Also The Structural Excavation.

We Started The Second Phase Of Mass Excavation on February 23, 2009. Our portion of this project should be completed by July 01, 2009.

We currently still have a little work to be done on the 100 S. Ramp area but our portion of the project is now 98% complete.

17th Street; Wall Ave to City Boundary

Ogden City, UT

Millcreek Drive Improvements

Moab, UT

Seep Ridge Road Segment III

Uintah County, Utah

Little Cottonwood Creek

Salt Lake County, Utah

I-15 South Layton Interchange Project

Layton, UT

SR-66 Weber River Morgan Bridge

Morgan, UT

City Creek Block 75 Project

Salt Lake City, UT

7800 South State Street Trax Bridge

Salt Lake City, Utah

Blue Sky Ranch

Wanship, Utah

Ellison Park

Layton, UT

Emmigration Bike Lanes

Emmigration Canyon, Utah

Draper LDS Temple

Draper, Utah

Trucking Division

Poverty Point, UT

Salt Lake City Library

Salt Lake City, UT

Cherry Hill Interchange

Fruit Heights, UT

Scenic Arizona Bridge & Road

Mojave County, AZ

Evanston Burns Field Airport Expansion

Evanston, WY

Debris Basin Corner Canyon

Salt Lake County, UT