We started this project back in November with Holder/Big-D and Ralph L. Wadsworth. Our portion of the project is excavating out for the Central Utility Tunnel. It is roughly 1100 feet in length, 140 feet in width and 34 feet in depth. Our portion, Phase I of the excavation is expected to be completed in April of 2021 and Phase II of the backfilling of the tunnel is expected to start in the Fall of 2021. We are excited to be working on this project and look forward to a successful project!